If 5 workers can pave 10 driveways in 30 days, how many days would it take 20 workers to pave 38 driveways?

Respuesta :

musiclover10045
musiclover10045 musiclover10045
  • 25-07-2017

5*30/10 = 20x/38

150/10 = 20x/38 =

5700/200x=

x= 5700/200 = 28.5 days

Answer Link

Otras preguntas

Coach Boone tells Coach Yoast “welcome to my life”, what he is mean by “my life”?
Kelly is attending physical therapy after knee surgery. She walked 9 1/4 miles over 3 days. How many miles is that per day?
someone please help with my math (ill give brainliest)
The study of principles that govern the efficient spatial allocation of economic resources and the resulting consequences is referred to as ______.
brenda found that a bedroom floor measures 5 yards long and 4 1/2 yards wide . how many square yards of carpet would she need to cover this floor
How can you use forces to affect different objects based on their masses?
Estimate the measure of this angle within 15 degree.
what is 24% as a whole number
Peter points out that one of the things he learned about planning the business is:.
Which major type of air mass is moving into the area? maritime polar continental polar maritime tropical continental tropical.