Ratio. Proportion and many method d) 15 workers were employed to complete a piece of work in 36 days. How many more workers should be added to complete the work in 30 days?​

Respuesta :

Аноним Аноним
  • 25-12-2021

Answer:

Step-by-step explanation:

total of 15(36) = 540 person•hours was used

540 / 30 = 18 people

18 - 15 = 3 people need to be added

Answer Link

Otras preguntas

what is 709÷31= and 50÷409
The nurse mentor is observing a novice nurse prepare to insert an indwelling catheter for a female client with urinary retention. the mentor would intervene, if
How does the valence of each element help you determine the structure of the glucose molecule?
Please help me with #20 and #22
what's (3×100)+(5×10)+5/10) in standard form? show work please
Which property justifies the following statement? 5(7z − 3y) = 35z − 15y
I have only 3hours to do this hellp me pls need the answer
A healthy adult can tolerate blood loss of up to ____ ml over a period of 15 to 20 minutes without any negative effects
Research indicates that minorities are most influential when they
describe the dimensions of a triangular prism that has a surface area between 550 square inches and 700 inches.