Planned value:

How is it calculated?

Respuesta :

ZaWarud0
ZaWarud0 ZaWarud0
  • 21-10-2020
Take the planned percentage of the completed work and multiply it by the project budget and you will get Planned Value.
Answer Link

Otras preguntas

meg has a new bookcase for her bedroom eith 6 shelves. Each shelf holds 8 books. If meg has 50 book, how many books will not fit on the bookcase​
help asap pleaseee ?:))
I also need to show my work so if somebody could help explain how i do that i’d appreciate it.
Simplify: A -6i B 6i (sqrt 2) C -6i (sqrt -2) D 6i
Someone help me please!! giving brianly award
The Bailey’s spent $18.00 for 4 two-liter sodas for the birthday party this weekend. What is the number of soda bottles that could be bought for $45.00?
What is rain shadow area? How does it occur?
The yllis only has three pairs of chromosomes but can produce many different possible gamete combinations. Think about humans, who have 23 pairs of chromosomes.
What is the temperature of the water at a cold seep? A. around 4°C B. around 20°C C. always below the freezing point of water D. hot, but much cooler than a
When an organ has a disease, it cannot function properly. What effect might a disease that affects the small intestine have on a person? The person might be un