30men can finish 1/7of a work in 2days.18men will do othe remaining work in ?

Respuesta :

chumxo chumxo
  • 24-09-2016
7/7-1/7=6/7 is the rest of work
1/7 work takes 2days
6*1/7=6/7 work takes 6*2days=12days
30 men takes 12 days to finish the rest of work (6/7)
18 men takes 18*12/30= 7.2days
Answer Link

Otras preguntas

Jim picks a number he doubles that number then adds five and gets 41 as his results what was the original number Jim picked
Which of the following is NOT positively influenced by physical activity? A. cardiovascular disease B. obesity C. osteoporosis D. allergies
Why is tolerance an important responsibility of citizenship
After the effects of the troop “surge” were felt in Iraq, President Bush
Let f(x) = -5x - 4 and g(x) = 6x - 7. Find f(x) + g(x)
write two expressions where solution is 19
Deborah found that six of the 24 students in her class on a cell phone what is the ratio of students that own a cell phone to students that do not
What's the verbal expression for the algebraic expression 1/8y .?
tahiti is an example of which type of island? A. high island B. low island C. continental island D. delta island
Ned is training for a biathlon. He will swim every sixth day and bicycle every eighth day. On what days will he both swim and bicycle?? Specified answers please