The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as

Respuesta :

topeadeniran2 topeadeniran2
  • 26-08-2020

Answer: template method

Explanation:

The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as template method.

It should be noted that estimating time and cost are vital because it helps schedule work, develop needs of cash flow and show progress of a project.

Answer Link

Otras preguntas

Factor completely x^2-3x-28
Which element would the search element be compared to first, if abinary search were used on the list above? 4 35 44 98
1 Point Which statement describes the energy conversion that takes place during photosynthesis? O A. Plants covert solar energy to kinetic energy. O B. Plants c
Petra is able to imagine what would happen if parents were held legally responsible for the crimes of their children. She is capable of making an argument for o
a beaker has mass of 125 g. what is the mass of liquid if the beaker plus liquid have a mass of 232 g?
A tennis ball bounces on the floor three times. If each time it loses 11% of its energy due to heating, how high does it rise after the third bounce, provided w
Solve the expression x^2-100=0
What is the slope of the line containing (6, -7) and (5, -9)? A) 1 B) -2. C) 2 D) 16
In Linux Operating System, what file extension is used forexecutable files?
The Input-output diagram represents F(x) = x - 3. What is the missing output value?