The Control Schedule process to ______________ completion of project work in a timely manner.

Respuesta :

ununseptiumaorta
ununseptiumaorta ununseptiumaorta
  • 03-10-2019

Answer:

The Control Schedule process to ensure completion of project work in a timely manner.

Explanation:

In managing the Project Schedule, the finalized and approved schedule represents the implemented basis for the development and direction of the schedule. On the other hand, in the time the project activities take place, most of the effort will also take place in this process to guarantee the fulfillment of the project on time.  

Answer Link

Otras preguntas

Which of these actions may be prohibited by a court, despite the First Amendment's guarantee of freedom of the press? O A. Publishing articles that are meant on
-2=n-4 how do you get n​
When El Niño occurs,​
Who has the most political power in Australia’s government
What percent of 30 is 1.5?
plz plz plz help me plz plz plz plz help help help me what is 5/7x+15-9/14x-9 What is the answer?
Read this passage from "The Chrysanthemums" by John Steinbeck: Elisa took off her gloves and stuffed them in the apron pocket with the scissors. She touched the
Firm F, a calendar year taxpayer, owes a $200,000 long-term debt to an unrelated creditor. In December, it paid $14,160 to the creditor as interest for the 12-m
1. True / False
What were the Articles of Confederation? What type of union did the Articles of Confederation create? What was one function of the central government under the