kenny7591 kenny7591
  • 22-02-2024
  • Mathematics
contestada

You work as a project coordinator for a design company. on one project, the status report shows that 10 of the work was completed in 90 days. if the work progresses at the same rate, how many days will be required to complete the remainder of the project?
a. 9 days
b. 80 days
c. 100 days
d. 810 days

Respuesta :

Otras preguntas

Can plants cause chemical weathering by breaking down soil during photosynthesis
156 is 60% of what number
9 more than the quotation of -36 and -4
At the zoo, there were 3 times as many monkeys as lions. Tom counted a total of 24 monkeys and lions. How many monkeys were there?
Which is an effective treatment for depression?
Once granted that Congress has the power to incorporate a bank, why did Chief Justice Marshall find that the state of Maryland could not, without violating the
Mr house wrote 8 tenths minus 5 hundredths on the board. Maggie said the answer is 3 hundredths because 8 minus 5 is 3. Is this correct?
RS bisects ∠QRT. If m∠QRT = 116, what is m∠QRS?
What kind of data should I record for an experiment testing whether snow protects leaves from cold temperature?
Susan's point total is greater than -25. Does Susan need more than 25 points are fewer than 25 points.