  • Mathematics
contestada

If a house takes 15 days to build with 8 workers working. How many days will it take if 4 additional workers are hired?

Respuesta :

Otras preguntas

A 1.0-m-tall vertical tube is filled with 20°C water. A tuning fork vibrating at 580 Hz is held just over the top of the tube as the water is slowly drained fro
Platinum has a molar mass of 195 g/mol. If you have a ring that contains 2.3 g of platinum, how many moles does it contain?
Solve the compound inequality, 2y-2>- 14 or 4y-4 ≥ 12 Write the solution in interval notation, If there is no solution, enter Ø.
factor please help 14-2y
i need help with b. How would the ordered pairs be different if the outdoor temperature were recorded every hour for 4 consecutive hours?
What is the definition of Standard Deviation? a. Square of the variance b. Square root of the variance c. Square of mean minus 1 d.
-ax + by = c, bx + ay = (1 + c)​
to be an angle in quadrant II such that cos O= -5/8 Find the exact values of csc O and cot O.
9. If one box of books contains 7.5% of the total shipment and each box includes 15 books, how many books are included in the total shipment! assuming every box
For a system containing a mixture of air and water, the wet-bulb temperature is the same as the adiabatic saturation temperature.